Post date: Aug 09, 2017 9:57:1 PM
A Final Grant of Planning Permission is expected later this week so that developments can continue on our new site at Carrick Esker.
As everyone is well aware our new pitches have really taken shape over the summer months and look great. We are very keen to get our teams onto the pitches and use them in anger. Our groundsmen led by Pat Cullen are doing a remarkable job in keeping the pitches in tip top condition.
In the coming weeks some key infrastructure will be installed;
4 sets of goals posts to be installed
4 ball stopper nets to be erected behind each goal
4 Dugouts
Pitch side fencing around pitches
Walking path surrounding pitches and site perimeter
New entrance wall & gates
Boundary fencing around perimeter
Parking layout & surface dressing
Ducting for future floodlighting
Service connections; electric, water & sewerage
Temporary dressing rooms installed.
Other elements such as the permanent dressing room building, floodlights & ball wall will be delivered in later phases.
This is an exciting phase and the site will really begin to take its final shape in the coming weeks. We are looking forward to hosting an open day for members supporters and Donor Wall members very soon.