Facilities Development

This page will contain information charting progress on the first phase of our development plan along with detailed information on our overall Master plan.....
SEPT' 17 - Works On-Going  
The first few weeks of September has seen more progress and the fencing etc. has commenced.  


AUG' 17 - Planning Permission Granted  
A Final Grant of Planning Permission is expected later this week  so that developments can continue on our new site at Carrick Esker. 

As everyone is well aware our new pitches have really taken shape over the summer months and look great.  We are very keen to get our teams onto the pitches and use them in anger. Our groundsmen led by Pat Cullen are doing a remarkable job in keeping the pitches in tip top condition. 

In the coming weeks some key infrastructure will be installed;
  • 4 sets of goals posts to be installed 
  • 4 ball stopper nets to be erected behind each goal 
  • 4 Dugouts
  • Pitch side fencing around pitches 
  • Walking path surrounding pitches and site perimeter 
  • New entrance wall & gates
  • Boundary fencing around perimeter 
  • Parking layout & surface dressing 
  • Ducting for future floodlighting 
  • Service connections; electric, water & sewerage 
  • Temporary dressing rooms installed. 
Other elements such as the permanent dressing room building, floodlights & ball wall will be delivered in later phases. 

This is an exciting phase and the site will really begin to take its final shape in the coming weeks.  We are looking forward to hosting an open day for members supporters and Donor Wall members very soon. 


JUN' 17 - Planning Application Update  
In April the club received a request for Further Information from Offaly Co. Co. in relation to certain aspects of our planning application.  In recent weeks we have been meeting with Officials from Offaly Co. Co. in order to resolve the outstanding issues.  We are pleased to announce that we have made a formal response and we are now due a decision by 13th July next.

We are hopeful of a positive decision and if successful we aim to immediately set about completing works on site.  This will involve the erection of new entrance, boundary fencing, goalposts, ball stops, pitch side fencing, pathways and car parking.

The pitches themselves are in excellent condition and are thickening up nicely.  Some of our adult teams will be using the pitches for training purposes shortly, however for health and safety reasons our underage teams won't be able to use the pitches until such time as all the works on site are complete.  At this stage we are hopeful this would be before the end of the season. 



APR' 17 - Planning Application Update  
In April the club received a request for Further Information from Offaly Co. Co. in relation to certain aspects of our planning application.  Unfortunately this introduces a delay to our programme of works but the Club will be working with our design team in the coming weeks to get the additional information together and lodged to the Council.  Once we make our response a decision will be due within four weeks. Log onto the Offaly Co. CO. Planning website to inspect the request  Offaly C. Co. Planning Search and search Ref. No.'s 17/62 & 17/63.

In any event the pitches need a few more weeks of growing in before they will be playable, however they are coming along nicely.  They have been fertilized and aerated in recent weeks and with temperatures set to rise next week the growth should follow. 

This picture from early April 2017 demonstrates progress and the pitches are currently being cut twice a week. 




FEB' 17 - Planning Application Lodged  
After many months of planning, liaison with the membership, wider community & Edenderry Swimming Pool our lead Architect Bernard Voortman lodged our planning application on Friday 17 Feb, following correction of our newspaper advert accompanying the application.

Indeed there are two planning applications lodged.  One for site A and one for Site B.  Both applications are very extensive and contain a huge amount of detail, including drawings for the pavilion renovation, dressing extension on site A and new dressing rooms on site B.   

The applications also show future floodlighting, an all weather facility and ball wall. The detail of the layout drawings can be viewed on the drawings below.  The full application can be viewed on the Offaly Co. Co. website CLICK HERE 

We hope to have an initial decision in around 8 weeks c. mid April.  

LOCATION MAP - Click on Map
Location Map Full Sized PDF

SITE A PROPOSED LAYOUT - Click on Map 
Click Here Full Sized PDF Site A

SITE B PROPOSED LAYOUT- Click on Map 
Click Here Full Sized PDF Site B


NOV' 16 - Continued Growth 
Following a mild Autumn the grass on both pitches has thickened up nicely and now as the growing season ends they will be aerated and re-fertilized ahead of the winter.  Looking good for seeing action by late Spring. 





OCT' 16 - Irish TV 
In 2015 Irish TV visited Edenderry to hear about the purchase of our new grounds and this week they returned for an update.  Te pitches have just gone through their first few cuts with our new mower and are looking great.  Our sports Turf Consultant was on hand to explain the process to Laura McCormack from Irish TV.  


OCT' 16 - New Tractor & Mower 
With the increased area to be maintained the club has invested in a new tractor and mower.  We just recently purchased a 1998 Ursus Mercury 450 Tractor with a Major Rigid Mower.  Great additions to our machinery and hopefully will work well. 


OCT' 16 - First Cut 
With ground temperatures remaining above normal both pitches are thriving.  Pitch No. 1 received its first cut last week and also fertilized to balance nutrient levels in the soil. Pitch No. 2 is thickening up nicely.
Pitch No. 1 on 8/10/16

Pitch No. 2 on 8/10/16

Pitch No. 1 on 23/09/16
SEPT' 16 - Pitch No. 2 Seeded 
Following the success of pitch No. 1 we were very keen to progress Pitch No. 2 and get it seeded before the end of September.  Fortunately the improved for a few days and on Saturday 17 September Pitch No. was seeded. The images below were taken on Wed. 28th Sept and progress was good. 





SEPT' 16 - Pitch No. 1 Progress 
The first 10 days post seeding of Pitch No. 1 provided ideal growing conditions and the pitch thrived.  The image below represents the progress made in a number of weeks.


SEPT' 16 - Pitch No. 1 Green Shoots 
The first green shoots began to appear on Pitch No. this week. The photo below was taken on Sat 10. Sept.  Hopefully this week will see an improvement in the weather to allow pitch No. 2 to be seeded. 


SEPT' 16 - Pitch No. 1 Seeded 
The first week of September witnessed an improvement in the site conditions and the weather.  This allowed John Foran and his team to commence the final sanding of pitch No. 1.  This involved a layer of 30mm of fine Wexford sand across the entire surface.  Following a process of 'tickling' the sand into the top layer of topsoil the pitch was re-levelled again. On Friday 02 Sept the pitch was intensively seeded with perennial rye grass seed.  


Depending on weather conditions it is hoped that green grass will begin shooting up in 10 days or so.  However, it will be the end of next Spring before the pitch will be playable. 

The final drainage works were also completed on Pitch No. 2 and its now ready for the final layer of sand and it is hoped it will be seeded by the middle of next week. 



AUG' 16 - OH Lines diverted and Slit Drainage 
Following heavy rain ESB Networks moved into site to remove the Overhead lines and two poles from the middle of the pitches. The new line which is a combination of new overhead and some underground now skirts the perimeter of the site.


Some repair works were required to the pitches following these works and de-stoning and fine levelling continued over the weekend.  

On Monday the 29th of August the first layer of sand was put on pitch No. 1 and the slit drainage was commenced.  With this good spell of weather some good progress can be made this week. 




AUG' 16 - Drainage Works 
This week saw the installation of pitch drainage across the two pitches.  In addition the ESB commenced works to divert the overhead line that currently traverses the site.  These diverson works will be complete on Tuesday and thus clearing the way to allow the final works to the pitches prior to seeding. 

Unfortunately the weather has taken a turn for the worst and days were lost this week due to inclement weather for the first time since the project started. Hopefully the weather can remain dry next week.


New ESB Poles erected around perimeter of site.

AUG' 16 - Stage 1 Complete 

Laser Levelling of Pitches - 12 Aug'16


Following 3 weeks of intensive works all of the topsoil has been distributed across the site and full site cleared and open.  The site has transformed in 3 weeks and with some hidden works, including the main drainage, its been a successful commencement to the project.

Over the weekend the pitch was laser levelled and the process of de-stoning has commenced. 

Next week the ESB will move in to divert the overhead line that traverses the site and this will leave and unimpeded site to progress with.  Busy few weeks ahead. 

JUL' 16 - Formal Launch of Works 
Members of the Committee of Edenderry GAA joined John Foran and his team from Emerald Pitch Developments Ltd. on site to inspect progress made in the first week and also to formal mark the appointment of Emerald Pitch Developments Ltd. as main contractor for the project. Check out our on-going photo album that will track progress with the project over the coming weeks. 
Club Chairman Willie Forde formally appoints John Foran of Emerald Pitch Developments Ltd. as main contractor t construct 2 pitches for Edenderry GAA. 

2 Sand based all weather pitches


JUL' 16 - Works Commence 
In an effort to move our ambitious plans forward, Edenderry GAA have commenced construction of two sand based grass pitches on our new lands.  This is the first step in an ambitious master plan.

Following a competitive tendering process under the supervision of our Turf Consultant Mr. Richard Hayden of Sportsturf Solutions, local contractor Emerald Pitch Developments was appointed Main Contractor for the project. 

In an effort to have the pitches ready for 2017 we have moved forward with this element of works by way of a Section 5 Declaration from Offaly Co. Co.  The earthworks and grass seeding are deemed exempted development and can commence prior to the lodgement of a planning application for the more permanent structure that will follow in the coming weeks. 

The works are expected to continue until Sept/Oct and are very dependent on weather.  We will provide constant updates here so check back regularly. 



APR' 16 - Huge Response to Fundraising Drive
The number of families and individuals already signed up to the Donor Wall is ahead of schedule at 130.  In April will focus on the Business Community and hope to be just as success with this ever supportive group.

If we slow to get to you and you are keen to sign up please download the attached Standing Order Form and return to one of our Project Champions.

The minimum donation in order to get your name on the wall remains at €250 for individuals and families.

The model for Businesses is slightly different and set out on the attached letter


MAR' 16 - Fundraising Drive Commences
As our plans and designs get close to completion our current programme estimates will see us commence construction on the two new pitches Site B this summer.
We shall be lodging our planning application in the coming weeks.
Our Fundraising Team will be working hard over the month of March to touch base with as many members and supporters as possible.  We are seeking donations to the project.  For as little as €25 euro a month for the remaining 10 months of 2016 you can make a significant contribution to the delivery of the two new pitches,
In return your name/family name will be permanently erected on our planned Donor Wall that will serve as a reminder to future generations of the vision of our current membership.
More details can be found in our promotional brochure - click the link below;
Click Here















JAN' 16 - Trial Holes & Site Investigations 
On 21st January Richard Hayden of Sports Turf Solutions attended site to investigate the soil conditions of our lands.  

The aim was to collect information on ground conditions and establish any potential constraints associated with the development.  This critical phase allows Sports Turf Solutions to independently review both sites and develop the following;

SITE A & B
  • Surface topsoil depth and indicative quantification for re-use 
  • Topsoil review & commentary on quality of topsoil on site (including heaped spoils)
  • Review pitch positioning & layout options
  • Pitch costs for development
  • Timeframe for works 
  • Future maintenance costs
This information will allow the club to move forward with the best solution possible. 

Local Machine Operator Noel Gorman was on hand to assist with the digging of the trial holes. 



OCT' 15 - Workshop Report 
Nearly 100 people attended the public planning workshop in the GAA Clubhouse on Tuesday 6th October 2015.  We had a great mix of people from our own active members, coaches & supporters, local residents, school teachers, Edenderry Swimming Pool Reps, Local County Councillors, Eden Tri Club Reps, Skateboard Park Reps and many others. 

Our Architects Bernard Voortman & Robert Cummins gave a detailed presentation on the proposed masterplan, including the initial site analysis, the results of the online survey and importantly their first draft of how they see the lands being developed.

The Architects proposals were very visual in nature and thus easy to understand.  They were very well received and instigated much debate and analysis from the floor.

Our facilitator for the evening Paul O'Kelly then took over to ensure that all ideas were captured from the debate.  Paul had a set of prepared questions that were discussed among small groups and the ideas and opinions were collected for the Architects.

It must be highlighted that the initial proposals are  open to change and we also wish to highlight the importance of our on-going discussions with Edenderry Swimming Pool to establish if common ground can be found so that the pool can expand at its current location.

The next steps are as follows;

1. Review Material from the Workshop and amend the initial design.

2. Meeting with the Swimming Pool Architectural Team to further work up common proposals.

3. Further update proposals and present to interested parties again.

All of the workshop material is downloadable from this site.


Older Development News
As of July 2015 we are meeting groups within the club, players, coaches, committee members etc.

We hope to meet local residents in the coming weeks to bring them up to speed with developments,

Before concluding our design process we will be hosting an open workshop for all members of the club and wider community to input to the design of our new facilities. 

Public Planning Workshop 
Tue 6th October 2015
Shape the Future, You Decide...
In conjunction with our architects Cummins & Voortman, Edenderry GAA extends an open invitation to the community to our club planning workshop. 

As designs advance for our new facilities we want your views and ideas.
What should we build?
Are community groups looking to share facilities? 
How will we fund it?
What should we prioritize? 


http://www.cvltd.ie/Home.html

Strategic Plan Launch Presentation - Apr'17
CLICK HERE

Pitch Development Progress

Fundraising Drive Continues
Follow This Link - Click Here

Latest Imagery - Detailed Design (Feb'16)

Detailed Design


Initial Concept Designs
Workshop No. 1 Material -  (6 Oct '15)

https://drive.google.com/file/d/0BxXpVG0EqwYLMnNxWDJWcWJBYm8/view?usp=sharing


https://drive.google.com/file/d/0BxXpVG0EqwYLVWZEczdCNG8yVE0/view?usp=sharing


https://drive.google.com/file/d/0BxXpVG0EqwYLNjlUWHk1UmNfQTQ/view?usp=sharing